Financial Summary |
|
Contract Amount: | |
Suggested Contribution: | |
Total Commitments Received: | $460,000.00 |
100% SP&R Approval: | Approved |
Contact Information |
|||
Lead Study Contact(s): | David Behzadpour | ||
David.Behzadpour@ks.gov | |||
Phone: 785-291-3847 | |||
FHWA Technical Liaison(s): | Reggie Holt | ||
Reggie.Holt@dot.gov | |||
Phone: 202-366-4596 | |||
Study Champion(s): | Mark Hoppe | ||
Hoppe@ksdot.org |
Organization | Year | Commitments | Technical Contact Name | Funding Contact Name |
---|---|---|---|---|
Federal Highway Administration | 2012 | $75,000.00 | Reggie Holt | Reggie Holt |
Florida Department of Transportation | 2012 | $10,000.00 | Sam Fallaha | Patti Brannon |
Florida Department of Transportation | 2013 | $10,000.00 | Sam Fallaha | Patti Brannon |
Florida Department of Transportation | 2014 | $10,000.00 | Sam Fallaha | Patti Brannon |
Idaho Department of Transportation | 2012 | $10,000.00 | Matt Farrar | Amanda Laib |
Idaho Department of Transportation | 2013 | $10,000.00 | Matt Farrar | Amanda Laib |
Idaho Department of Transportation | 2014 | $10,000.00 | Matt Farrar | Amanda Laib |
Iowa Department of Transportation | 2013 | $10,000.00 | Norm McDonald | -- -- |
Iowa Department of Transportation | 2014 | $10,000.00 | Norm McDonald | -- -- |
Iowa Department of Transportation | 2015 | $10,000.00 | Norm McDonald | -- -- |
Kansas Department of Transportation | 2012 | $10,000.00 | Loren Risch | David Behzadpour |
Kansas Department of Transportation | 2013 | $10,000.00 | Loren Risch | David Behzadpour |
Kansas Department of Transportation | 2014 | $10,000.00 | Loren Risch | David Behzadpour |
Louisiana Department of Transportation and Development | 2012 | $10,000.00 | Hossein Ghara | Harold Paul |
Louisiana Department of Transportation and Development | 2013 | $10,000.00 | Hossein Ghara | Harold Paul |
Louisiana Department of Transportation and Development | 2014 | $10,000.00 | Hossein Ghara | Harold Paul |
Michigan Department of Transportation | 2013 | $10,000.00 | Matthew Chynoweth | Andre' Clover |
Michigan Department of Transportation | 2014 | $10,000.00 | Matthew Chynoweth | Andre' Clover |
Michigan Department of Transportation | 2015 | $10,000.00 | Matthew Chynoweth | Andre' Clover |
Minnesota Department of Transportation | $0.00 | |||
Nebraska Department of Transportation | 2013 | $10,000.00 | Mark Traynowicz | Jodi Gibson |
Nebraska Department of Transportation | 2014 | $10,000.00 | Mark Traynowicz | Jodi Gibson |
Nebraska Department of Transportation | 2015 | $10,000.00 | Mark Traynowicz | Jodi Gibson |
New Jersey Department of Transportation | 2012 | $10,000.00 | J.Eric Kraehenbuehl,PE | Edward Kondrath |
Ohio Department of Transportation | 2012 | $10,000.00 | Waseem Khalifa | General Research |
Ohio Department of Transportation | 2013 | $10,000.00 | Waseem Khalifa | General Research |
Oregon Department of Transportation | 2013 | $5,000.00 | Jan Six | Michael Bufalino |
Pennsylvania Department of Transportation | 2012 | $10,000.00 | Tom Macioce | Lisa Tarson |
Pennsylvania Department of Transportation | 2013 | $10,000.00 | Tom Macioce | Lisa Tarson |
Pennsylvania Department of Transportation | 2014 | $10,000.00 | Tom Macioce | Lisa Tarson |
Texas Department of Transportation | 2013 | $10,000.00 | John Holt | Ned Mattila |
Texas Department of Transportation | 2014 | $10,000.00 | John Holt | Ned Mattila |
Texas Department of Transportation | 2015 | $10,000.00 | John Holt | Ned Mattila |
Utah Department of Transportation | 2013 | $10,000.00 | Joshua Sletten | David Stevens |
Utah Department of Transportation | 2014 | $10,000.00 | Joshua Sletten | David Stevens |
Utah Department of Transportation | 2015 | $10,000.00 | Joshua Sletten | David Stevens |
Virginia Department of Transportation | 2013 | $10,000.00 | Prasad Nallapaneni | Bill Kelsh |
Virginia Department of Transportation | 2014 | $10,000.00 | Prasad Nallapaneni | Bill Kelsh |
Virginia Department of Transportation | 2015 | $10,000.00 | Prasad Nallapaneni | Bill Kelsh |
Washington State Department of Transportation | 2013 | $10,000.00 | Kim Willoughby | Kristy Vargas |
Washington State Department of Transportation | 2014 | $10,000.00 | Kim Willoughby | Kristy Vargas |
Since the adoption of the AASHTO LRFD Bridge Design Specifications, 1st Edition, in 1992, yearly interim revisions have been written to Section 5, Concrete Structures, by members of the AASHTO technical committee T-10, Concrete Design; researchers or other friends of the committee. Much care was taken by the original National Cooperative Highway Research Program (NCHRP) project 12-33 team to maintain organizational, philosophical and technical consistency throughout the specifications. The yearly interim revisions since 1992, while well meaning, have not always maintained this consistency. The situation is not unique to Section 5. Indeed, AASHTO technical committee T-14, Structural Steel Design, had the opportunity to reorganize Section 6, Steel Structures, during their recent integration of straight and horizontally curved steel girders. Section 5 is also ready to be re-organized after these many years of interim revisions. The following tasks are proposed to develop a revised and reorganized Section 5:
The purpose of this project is to reorganize Section 5, Concrete Structures, of the AASHTO LRFD Bridge Design Specification so that Section 5 is logically organized, and philosophically and technically consistent. The entire LRFD Bridge Design Specification and AASHTO Bridge Construction Specification must be reviewed and updated as necessary to maintain consistency
This research project would be carried out in six tasks: 1. Survey stakeholders - Stakeholders will be identified and surveyed via conference calls and in-person meetings (for example, during the various T-10 meetings through the year) to identify the needs for returning Section 5 to its original consistency of organization, philosophy and technique. Stakeholders will include AASHTO technical committee T-10, practicing bridge-design engineers, and bridge-design researchers, among others. 2. Develop annotated revised table of contents - With input from Task 1, an annotated revised table of contents will be developed for Section 5. 3. Critically review all interim changes for technical and philosophical consistency - All interim changes since the original first edition of the LRFD Specifications will be reviewed for technical and philosophical consistency. 4. Write interim report - An interim report will be written proposing the revised table of contents and changes to the specifications to restore its philosophical and technical consistency. After review and approval of the interim report by T-10, Task 5 will begin. 5. Develop new revised and reorganized draft Section 5, Concrete Structures - Based upon the comments and direction of T-10 based upon the review of the interim report, a new revised and reorganized draft Section 5 will be developed. After review and approval of the draft section by T-10, Task 6 will begin 6. Develop final Section 5, Concrete Structures - Based upon the comments and suggestions of T-10, the final draft of Section 5 will be developed along with an accompanying agenda item for consideration by T-10 and subsequently the AASHTO Subcommittee on Bridges and Structures (SCOBS).
Section 5 has not been reviewed globally for 20 years. The project will review and restore Section 5 of the LRFD Bridge Design Specification so that it is technically sound and designers find it intuitive and easy to use. Estimated budget: $250,000. 100% SPR Approval has been requested. Participating states to commit $10,000 each year for two or three years.
No document attached.
General Information |
|
Study Number: | TPF-5(271) |
Lead Organization: | Kansas Department of Transportation |
Solicitation Number: | 1326 |
Partners: | FHWA, FL, IADOT, ID, KS, LA, MI, MN, NE, NJ, OH, OR, PADOT, TX, UT, VA, WA |
Status: | Closed |
Est. Completion Date: | |
Contract/Other Number: | |
Last Updated: | Nov 12, 2015 |
Contract End Date: |
Financial Summary |
|
Contract Amount: | |
Total Commitments Received: | $460,000.00 |
100% SP&R Approval: |
Contact Information |
|||
Lead Study Contact(s): | David Behzadpour | ||
David.Behzadpour@ks.gov | |||
Phone: 785-291-3847 | |||
FHWA Technical Liaison(s): | Reggie Holt | ||
Reggie.Holt@dot.gov | |||
Phone: 202-366-4596 |
Organization | Year | Commitments | Technical Contact Name | Funding Contact Name | Contact Number | Email Address |
---|---|---|---|---|---|---|
Federal Highway Administration | 2012 | $75,000.00 | Reggie Holt | Reggie Holt | 202-366-4596 | Reggie.Holt@dot.gov |
Florida Department of Transportation | 2012 | $10,000.00 | Sam Fallaha | Patti Brannon | 850-414-4616 | patti.brannon@dot.state.fl.us |
Florida Department of Transportation | 2013 | $10,000.00 | Sam Fallaha | Patti Brannon | 850-414-4616 | patti.brannon@dot.state.fl.us |
Florida Department of Transportation | 2014 | $10,000.00 | Sam Fallaha | Patti Brannon | 850-414-4616 | patti.brannon@dot.state.fl.us |
Idaho Department of Transportation | 2012 | $10,000.00 | Matt Farrar | Amanda Laib | 208-334-8181 | amanda.laib@itd.idaho.gov |
Idaho Department of Transportation | 2013 | $10,000.00 | Matt Farrar | Amanda Laib | 208-334-8181 | amanda.laib@itd.idaho.gov |
Idaho Department of Transportation | 2014 | $10,000.00 | Matt Farrar | Amanda Laib | 208-334-8181 | amanda.laib@itd.idaho.gov |
Iowa Department of Transportation | 2013 | $10,000.00 | Norm McDonald | -- -- | -- | Transfer.Research@iowadot.us |
Iowa Department of Transportation | 2014 | $10,000.00 | Norm McDonald | -- -- | -- | Transfer.Research@iowadot.us |
Iowa Department of Transportation | 2015 | $10,000.00 | Norm McDonald | -- -- | -- | Transfer.Research@iowadot.us |
Kansas Department of Transportation | 2012 | $10,000.00 | Loren Risch | David Behzadpour | 785-291-3847 | David.Behzadpour@ks.gov |
Kansas Department of Transportation | 2013 | $10,000.00 | Loren Risch | David Behzadpour | 785-291-3847 | David.Behzadpour@ks.gov |
Kansas Department of Transportation | 2014 | $10,000.00 | Loren Risch | David Behzadpour | 785-291-3847 | David.Behzadpour@ks.gov |
Louisiana Department of Transportation and Development | 2012 | $10,000.00 | Hossein Ghara | Harold Paul | 225-767-9101 | harold.paul@la.gov |
Louisiana Department of Transportation and Development | 2013 | $10,000.00 | Hossein Ghara | Harold Paul | 225-767-9101 | harold.paul@la.gov |
Louisiana Department of Transportation and Development | 2014 | $10,000.00 | Hossein Ghara | Harold Paul | 225-767-9101 | harold.paul@la.gov |
Michigan Department of Transportation | 2013 | $10,000.00 | Matthew Chynoweth | Andre' Clover | 517-749-9001 | clovera@michigan.gov |
Michigan Department of Transportation | 2014 | $10,000.00 | Matthew Chynoweth | Andre' Clover | 517-749-9001 | clovera@michigan.gov |
Michigan Department of Transportation | 2015 | $10,000.00 | Matthew Chynoweth | Andre' Clover | 517-749-9001 | clovera@michigan.gov |
Nebraska Department of Transportation | 2013 | $10,000.00 | Mark Traynowicz | Jodi Gibson | 402-479-4337 | jodi.gibson@nebraska.gov |
Nebraska Department of Transportation | 2014 | $10,000.00 | Mark Traynowicz | Jodi Gibson | 402-479-4337 | jodi.gibson@nebraska.gov |
Nebraska Department of Transportation | 2015 | $10,000.00 | Mark Traynowicz | Jodi Gibson | 402-479-4337 | jodi.gibson@nebraska.gov |
New Jersey Department of Transportation | 2012 | $10,000.00 | J.Eric Kraehenbuehl,PE | Edward Kondrath | 609-530-2058 | Ed.Kondrath@dot.state.nj.us |
Ohio Department of Transportation | 2012 | $10,000.00 | Waseem Khalifa | General Research | 614-644-8135 | Research@dot.state.oh.us |
Ohio Department of Transportation | 2013 | $10,000.00 | Waseem Khalifa | General Research | 614-644-8135 | Research@dot.state.oh.us |
Oregon Department of Transportation | 2013 | $5,000.00 | Jan Six | Michael Bufalino | 503-986-2845 | Michael.Bufalino@odot.oregon.gov |
Pennsylvania Department of Transportation | 2012 | $10,000.00 | Tom Macioce | Lisa Tarson | (717) 705-2202 | ltarson@pa.gov |
Pennsylvania Department of Transportation | 2013 | $10,000.00 | Tom Macioce | Lisa Tarson | (717) 705-2202 | ltarson@pa.gov |
Pennsylvania Department of Transportation | 2014 | $10,000.00 | Tom Macioce | Lisa Tarson | (717) 705-2202 | ltarson@pa.gov |
Texas Department of Transportation | 2013 | $10,000.00 | John Holt | Ned Mattila | 512-416-4727 | ned.mattila@txdot.gov |
Texas Department of Transportation | 2014 | $10,000.00 | John Holt | Ned Mattila | 512-416-4727 | ned.mattila@txdot.gov |
Texas Department of Transportation | 2015 | $10,000.00 | John Holt | Ned Mattila | 512-416-4727 | ned.mattila@txdot.gov |
Utah Department of Transportation | 2013 | $10,000.00 | Joshua Sletten | David Stevens | 801-589-8340 | davidstevens@utah.gov |
Utah Department of Transportation | 2014 | $10,000.00 | Joshua Sletten | David Stevens | 801-589-8340 | davidstevens@utah.gov |
Utah Department of Transportation | 2015 | $10,000.00 | Joshua Sletten | David Stevens | 801-589-8340 | davidstevens@utah.gov |
Virginia Department of Transportation | 2013 | $10,000.00 | Prasad Nallapaneni | Bill Kelsh | 434-293-1934 | Bill.Kelsh@VDOT.Virginia.gov |
Virginia Department of Transportation | 2014 | $10,000.00 | Prasad Nallapaneni | Bill Kelsh | 434-293-1934 | Bill.Kelsh@VDOT.Virginia.gov |
Virginia Department of Transportation | 2015 | $10,000.00 | Prasad Nallapaneni | Bill Kelsh | 434-293-1934 | Bill.Kelsh@VDOT.Virginia.gov |
Washington State Department of Transportation | 2013 | $10,000.00 | Kim Willoughby | Kristy Vargas | VargasK@wsdot.wa.gov | |
Washington State Department of Transportation | 2014 | $10,000.00 | Kim Willoughby | Kristy Vargas | VargasK@wsdot.wa.gov |
Since the adoption of the AASHTO LRFD Bridge Design Specifications, 1st Edition, in 1992, yearly interim revisions have been written to Section 5, Concrete Structures, by members of the AASHTO technical committee T-10, Concrete Design; researchers or other friends of the committee. Much care was taken by the original National Cooperative Highway Research Program (NCHRP) project 12-33 team to maintain organizational, philosophical and technical consistency throughout the specifications. The yearly interim revisions since 1992, while well meaning, have not always maintained this consistency. The situation is not unique to Section 5. Indeed, AASHTO technical committee T-14, Structural Steel Design, had the opportunity to reorganize Section 6, Steel Structures, during their recent integration of straight and horizontally curved steel girders. Section 5 is also ready to be re-organized after these many years of interim revisions. The following tasks are proposed to develop a revised and reorganized Section 5:
The purpose of this project is to reorganize Section 5, Concrete Structures, of the AASHTO LRFD Bridge Design Specification so that Section 5 is logically organized, and philosophically and technically consistent. The entire LRFD Bridge Design Specification and AASHTO Bridge Construction Specification must be reviewed and updated as necessary to maintain consistency
This research project would be carried out in six tasks: 1. Survey stakeholders - Stakeholders will be identified and surveyed via conference calls and in-person meetings (for example, during the various T-10 meetings through the year) to identify the needs for returning Section 5 to its original consistency of organization, philosophy and technique. Stakeholders will include AASHTO technical committee T-10, practicing bridge-design engineers, and bridge-design researchers, among others. 2. Develop annotated revised table of contents - With input from Task 1, an annotated revised table of contents will be developed for Section 5. 3. Critically review all interim changes for technical and philosophical consistency - All interim changes since the original first edition of the LRFD Specifications will be reviewed for technical and philosophical consistency. 4. Write interim report - An interim report will be written proposing the revised table of contents and changes to the specifications to restore its philosophical and technical consistency. After review and approval of the interim report by T-10, Task 5 will begin. 5. Develop new revised and reorganized draft Section 5, Concrete Structures - Based upon the comments and direction of T-10 based upon the review of the interim report, a new revised and reorganized draft Section 5 will be developed. After review and approval of the draft section by T-10, Task 6 will begin 6. Develop final Section 5, Concrete Structures - Based upon the comments and suggestions of T-10, the final draft of Section 5 will be developed along with an accompanying agenda item for consideration by T-10 and subsequently the AASHTO Subcommittee on Bridges and Structures (SCOBS).
Section 5 has not been reviewed globally for 20 years. The project will review and restore Section 5 of the LRFD Bridge Design Specification so that it is technically sound and designers find it intuitive and easy to use. Estimated budget: $250,000. 100% SPR Approval has been requested. Participating states to commit $10,000 each year for two or three years.
Title | File/Link | Type | Private |
---|---|---|---|
TPF-5(271) Closeout Letter | TPF-5(271) Close out Memo - Signed.pdf | Memorandum | Public |
TPF-5(271) Closeout Funding Spreadsheet | TPF 5(271) Closeout Funding Spreadsheet.pdf | Other | Public |
Sept 2015 Quarterly Report | TPF AASHTO 2015 3rd Quarter Report .pdf | Progress Report | Public |
Quarterly Report Sept 2014 | TPF 2014 3rd-Quarter Report.pdf | Progress Report | Public |
Quarterly Report June 2014 | TPF 2014 2nd-Quarter Report.pdf | Progress Report | Public |
December 2013 Quarterly Report | TPF 2013 4th-Quarter Report.pdf | Progress Report | Public |
Quarterly Report October 2013 | TPF 5(271) Quarter Report Oct 2013.pdf | Progress Report | Public |
Quarterly Report June 2013 | TPF 5(271) Quarter Report June 2013.pdf | Progress Report | Public |
Quarterly Report March 2013 | TPF 5(271) Quarter Report April 2013.pdf | Progress Report | Public |
Quarterly Report Dec 2012 | TPF 5(271) Quarterly dec 2012.pdf | Progress Report | Public |
Acceptance Letter | TPF-5(271) Acceptance Letter.pdf | Memorandum | Public |