Financial Summary |
|
Contract Amount: | $995,000.00 |
Suggested Contribution: | |
Total Commitments Received: | $950,000.00 |
100% SP&R Approval: | Approved |
Contact Information |
|||
Lead Study Contact(s): | Rodney Montney | ||
rodney@ksdot.org | |||
Phone: 785-291-3844 |
Organization | Year | Commitments | Technical Contact Name | Funding Contact Name |
---|---|---|---|---|
Delaware Department of Transportation | 2003 | $25,000.00 | Joseph Cantalupo | |
Federal Highway Administration | 2002 | $60,000.00 | David Pamplin | |
Idaho Department of Transportation | 2003 | $15,000.00 | Matt Farrar | Mike Santi |
Idaho Department of Transportation | 2004 | $15,000.00 | Matt Farrar | Mike Santi |
Idaho Department of Transportation | 2005 | $15,000.00 | Matt Farrar | Mike Santi |
Idaho Department of Transportation | 2006 | $15,000.00 | Matt Farrar | Mike Santi |
Indiana Department of Transportation | 2003 | $15,000.00 | Tommy Nantung | |
Indiana Department of Transportation | 2004 | $15,000.00 | Tommy Nantung | |
Indiana Department of Transportation | 2005 | $15,000.00 | Tommy Nantung | |
Indiana Department of Transportation | 2006 | $15,000.00 | Tommy Nantung | |
Kansas Department of Transportation | 2003 | $50,000.00 | Rodney Montney | |
Michigan Department of Transportation | 2003 | $30,000.00 | Jon Reincke | |
Michigan Department of Transportation | 2004 | $30,000.00 | Jon Reincke | |
Minnesota Department of Transportation | 2002 | $15,000.00 | Dave Johnson | |
Minnesota Department of Transportation | 2003 | $15,000.00 | Dave Johnson | |
Minnesota Department of Transportation | 2004 | $15,000.00 | Dave Johnson | |
Minnesota Department of Transportation | 2005 | $15,000.00 | Dave Johnson | |
Mississippi Department of Transportation | 2003 | $15,000.00 | James Watkins | |
Mississippi Department of Transportation | 2004 | $15,000.00 | James Watkins | |
Mississippi Department of Transportation | 2005 | $15,000.00 | James Watkins | |
Mississippi Department of Transportation | 2006 | $15,000.00 | James Watkins | |
Missouri Department of Transportation | 2002 | $15,000.00 | Mara Campbell | |
Missouri Department of Transportation | 2003 | $15,000.00 | Mara Campbell | |
Missouri Department of Transportation | 2004 | $15,000.00 | Mara Campbell | |
Montana Department of Transportation | 2002 | $15,000.00 | Kent Barnes | Susan Sillick |
Montana Department of Transportation | 2003 | $15,000.00 | Kent Barnes | Susan Sillick |
Montana Department of Transportation | 2004 | $15,000.00 | Kent Barnes | Susan Sillick |
Montana Department of Transportation | 2005 | $15,000.00 | Kent Barnes | Susan Sillick |
New Hampshire Department of Transportation | 2003 | $15,000.00 | Glenn Roberts | |
New Hampshire Department of Transportation | 2004 | $15,000.00 | Glenn Roberts | |
New Hampshire Department of Transportation | 2005 | $15,000.00 | Glenn Roberts | |
New Hampshire Department of Transportation | 2006 | $15,000.00 | Glenn Roberts | |
North Dakota Department of Transportation | 2002 | $10,000.00 | Ron Horner | |
North Dakota Department of Transportation | 2003 | $10,000.00 | Ron Horner | |
North Dakota Department of Transportation | 2004 | $10,000.00 | Ron Horner | |
North Dakota Department of Transportation | 2005 | $10,000.00 | Ron Horner | |
Oklahoma Transportation | 2003 | $20,000.00 | Walter Peters | Ginger McGovern |
Oklahoma Transportation | 2004 | $20,000.00 | Walter Peters | Ginger McGovern |
Oklahoma Transportation | 2005 | $20,000.00 | Walter Peters | Ginger McGovern |
South Dakota Department of Transportation | 2003 | $40,000.00 | David Huft | |
Texas Department of Transportation | 2002 | $50,000.00 | Paul Krugler | |
Texas Department of Transportation | 2003 | $50,000.00 | Paul Krugler | |
Texas Department of Transportation | 2004 | $50,000.00 | Paul Krugler | |
Texas Department of Transportation | 2005 | $50,000.00 | Paul Krugler | |
Wyoming Department of Transportation | 2002 | $10,000.00 | Michael Patritch |
To implement the most cost-effective techniques for improving bridge deck life through the reduction of cracking.
Subjects: Bridges, Other Structures, and Hydraulics and Hydrology
No document attached.
General Information |
|
Study Number: | TPF-5(051) |
Lead Organization: | Kansas Department of Transportation |
Contract Start Date: | Sep 01, 2002 |
Solicitation Number: | 748 |
Partners: | DE, FHWA, ID, IN, KS, MI, MN, MO, MS, MT, ND, NHDOT, OK, SD, TX, WY |
Contractor(s): | University of Kansas |
Status: | Closed |
Est. Completion Date: | |
Contract/Other Number: | TPF-5(174) |
Last Updated: | Sep 12, 2011 |
Contract End Date: | Mar 31, 2010 |
Financial Summary |
|
Contract Amount: | $995,000.00 |
Total Commitments Received: | $950,000.00 |
100% SP&R Approval: |
Contact Information |
|||
Lead Study Contact(s): | Rodney Montney | ||
rodney@ksdot.org | |||
Phone: 785-291-3844 |
Organization | Year | Commitments | Technical Contact Name | Funding Contact Name | Contact Number | Email Address |
---|---|---|---|---|---|---|
Delaware Department of Transportation | 2003 | $25,000.00 | Joseph Cantalupo | 302-760-2112 | jcantalupo@mail.dot.state.de.us | |
Federal Highway Administration | 2002 | $60,000.00 | David Pamplin | david.pamplin@dot.gov | ||
Idaho Department of Transportation | 2003 | $15,000.00 | Matt Farrar | Mike Santi | 208- 334-8450 | mike.santi@itd.idaho.gov |
Idaho Department of Transportation | 2004 | $15,000.00 | Matt Farrar | Mike Santi | 208- 334-8450 | mike.santi@itd.idaho.gov |
Idaho Department of Transportation | 2005 | $15,000.00 | Matt Farrar | Mike Santi | 208- 334-8450 | mike.santi@itd.idaho.gov |
Idaho Department of Transportation | 2006 | $15,000.00 | Matt Farrar | Mike Santi | 208- 334-8450 | mike.santi@itd.idaho.gov |
Indiana Department of Transportation | 2003 | $15,000.00 | Tommy Nantung | 765-463-1521 ext 248 | tnantung@indot.in.gov | |
Indiana Department of Transportation | 2004 | $15,000.00 | Tommy Nantung | 765-463-1521 ext 248 | tnantung@indot.in.gov | |
Indiana Department of Transportation | 2005 | $15,000.00 | Tommy Nantung | 765-463-1521 ext 248 | tnantung@indot.in.gov | |
Indiana Department of Transportation | 2006 | $15,000.00 | Tommy Nantung | 765-463-1521 ext 248 | tnantung@indot.in.gov | |
Kansas Department of Transportation | 2003 | $50,000.00 | Rodney Montney | 785-291-3844 | rodney@ksdot.org | |
Michigan Department of Transportation | 2003 | $30,000.00 | Jon Reincke | 517-322-5695 | reinckej@michigan.gov | |
Michigan Department of Transportation | 2004 | $30,000.00 | Jon Reincke | 517-322-5695 | reinckej@michigan.gov | |
Minnesota Department of Transportation | 2002 | $15,000.00 | Dave Johnson | 651-282-2270 | dave.johnson@dot.state.mn.us | |
Minnesota Department of Transportation | 2003 | $15,000.00 | Dave Johnson | 651-282-2270 | dave.johnson@dot.state.mn.us | |
Minnesota Department of Transportation | 2004 | $15,000.00 | Dave Johnson | 651-282-2270 | dave.johnson@dot.state.mn.us | |
Minnesota Department of Transportation | 2005 | $15,000.00 | Dave Johnson | 651-282-2270 | dave.johnson@dot.state.mn.us | |
Mississippi Department of Transportation | 2003 | $15,000.00 | James Watkins | 601-359-7650 | jwatkins@mdot.state.ms.us | |
Mississippi Department of Transportation | 2004 | $15,000.00 | James Watkins | 601-359-7650 | jwatkins@mdot.state.ms.us | |
Mississippi Department of Transportation | 2005 | $15,000.00 | James Watkins | 601-359-7650 | jwatkins@mdot.state.ms.us | |
Mississippi Department of Transportation | 2006 | $15,000.00 | James Watkins | 601-359-7650 | jwatkins@mdot.state.ms.us | |
Missouri Department of Transportation | 2002 | $15,000.00 | Mara Campbell | 573-526-6687 | mara.campbell@modot.mo.gov | |
Missouri Department of Transportation | 2003 | $15,000.00 | Mara Campbell | 573-526-6687 | mara.campbell@modot.mo.gov | |
Missouri Department of Transportation | 2004 | $15,000.00 | Mara Campbell | 573-526-6687 | mara.campbell@modot.mo.gov | |
Montana Department of Transportation | 2002 | $15,000.00 | Kent Barnes | Susan Sillick | 406-444-7693 | ssillick@mt.gov |
Montana Department of Transportation | 2003 | $15,000.00 | Kent Barnes | Susan Sillick | 406-444-7693 | ssillick@mt.gov |
Montana Department of Transportation | 2004 | $15,000.00 | Kent Barnes | Susan Sillick | 406-444-7693 | ssillick@mt.gov |
Montana Department of Transportation | 2005 | $15,000.00 | Kent Barnes | Susan Sillick | 406-444-7693 | ssillick@mt.gov |
New Hampshire Department of Transportation | 2003 | $15,000.00 | Glenn Roberts | 603-271-3151 | Glenn.Roberts@dot.nh.gov | |
New Hampshire Department of Transportation | 2004 | $15,000.00 | Glenn Roberts | 603-271-3151 | Glenn.Roberts@dot.nh.gov | |
New Hampshire Department of Transportation | 2005 | $15,000.00 | Glenn Roberts | 603-271-3151 | Glenn.Roberts@dot.nh.gov | |
New Hampshire Department of Transportation | 2006 | $15,000.00 | Glenn Roberts | 603-271-3151 | Glenn.Roberts@dot.nh.gov | |
North Dakota Department of Transportation | 2002 | $10,000.00 | Ron Horner | 701-328-6904 | rhorner@nd.gov | |
North Dakota Department of Transportation | 2003 | $10,000.00 | Ron Horner | 701-328-6904 | rhorner@nd.gov | |
North Dakota Department of Transportation | 2004 | $10,000.00 | Ron Horner | 701-328-6904 | rhorner@nd.gov | |
North Dakota Department of Transportation | 2005 | $10,000.00 | Ron Horner | 701-328-6904 | rhorner@nd.gov | |
Oklahoma Transportation | 2003 | $20,000.00 | Walter Peters | Ginger McGovern | 405- 522-1447 | gmcgovern@odot.org |
Oklahoma Transportation | 2004 | $20,000.00 | Walter Peters | Ginger McGovern | 405- 522-1447 | gmcgovern@odot.org |
Oklahoma Transportation | 2005 | $20,000.00 | Walter Peters | Ginger McGovern | 405- 522-1447 | gmcgovern@odot.org |
South Dakota Department of Transportation | 2003 | $40,000.00 | David Huft | 605-773-3358 | dave.huft@state.sd.us | |
Texas Department of Transportation | 2002 | $50,000.00 | Paul Krugler | 512-465-7632 | pkrugle@dot.state.tx.us | |
Texas Department of Transportation | 2003 | $50,000.00 | Paul Krugler | 512-465-7632 | pkrugle@dot.state.tx.us | |
Texas Department of Transportation | 2004 | $50,000.00 | Paul Krugler | 512-465-7632 | pkrugle@dot.state.tx.us | |
Texas Department of Transportation | 2005 | $50,000.00 | Paul Krugler | 512-465-7632 | pkrugle@dot.state.tx.us | |
Wyoming Department of Transportation | 2002 | $10,000.00 | Michael Patritch | 307-777-4182 | michael.patritch@dot.state.wy.us |
To implement the most cost-effective techniques for improving bridge deck life through the reduction of cracking.
Subjects: Bridges, Other Structures, and Hydraulics and Hydrology
Title | File/Link | Type | Private |
---|---|---|---|
Development and Construction of Low-Cracking High-Performance Concrete (LC-HPC) Bridge Decks: Free Shrinkage, Mixture Optimization, and Concrete Production | SM92r.pdf | TPF Study Documentation | Public |
Development and Construction of Low-Cracking High-Performance Concrete (LC-HPC) Bridge Decks: Construction Methods, Specifications, and Resistance to Chloride Ion Penetration | SM94.pdf | TPF Study Documentation | Public |
Lightweight Aggregates as an Internal Curing Agent for Low-Cracking High-Performance Concrete | SM97Reynolds.pdf | TPF Study Documentation | Public |
Quarterly Report: January - March 2010 | SPR_quarterly_reportTPF-5(051)3-30-10a.pdf | Progress Report | Public |
Quarterly Report: 12-31-2009 | qtrly_rpt_12-31-09.pdf | Progress Report | Public |
Quarterly Report: 9-30-2009 | qtrly_rpt_09-30-09.pdf | Progress Report | Public |
Quarterly Report: 6-30-2009 | qtrly_rpt_09-06-30.pdf | Progress Report | Public |
Quarterly Report: 3-31-2009 | qtrly_rpt_03-31-09.pdf | Progress Report | Public |
Quarterly Report: 12-31-2008 | qtrly_rpt_12-31-08.pdf | Progress Report | Public |
Quarterly Report: 9-30-2008 | qtrly_rpt_09-30-08.pdf | Progress Report | Public |
Quarterly Report: 6-30-2008 | qtrly_rpt_06-30-08.pdf | Progress Report | Public |
Quarterly Report: 3-31-2008 | qtrly_rpt_03-31-08.pdf | Progress Report | Public |
Agreement and Proposal Modification No.1 (4/3/03) | Modification-1_to_KU_TPF-5_051.pdf | TPF Study Documentation | Public |
Agreement and Proposal Modification No.2 (3/13/08) | Modification-2_to_KU_TPF-5_051.pdf | TPF Study Documentation | Public |
Quarterly Report: 12-31-2007 | qtrly_rpt_12-31-07.pdf | Progress Report | Public |
Quarterly Report: 9-30-2007 | qtrly_rpt_09-30-07.pdf | Progress Report | Public |
Quarterly Report: 06-30-2007 | qtrly_rpt_06-30-07.pdf | Progress Report | Public |
Evaluating Free Shrinkage of Concrete for Control of Cracking in Bridge Decks - SM Report 89 | Research_Report_SM89.pdf | TPF Study Documentation | Public |
Evaluating Shrinkage and Cracking Behavior of Concrete Using Restrained Ring and Free Shrinkage Tests - SM Report 77 | Research_Report_SM77.pdf | TPF Study Documentation | Public |
Quarterly Report: 3-31-2007 | qtrly_rpt_03-31-07.pdf | Progress Report | Public |
Quarterly Report: 12-31-2006 | qtrly_rpt_12-31-06.pdf | Progress Report | Public |
Quarterly Report: 09-30-2006 | qtrly_rpt_09-30-06.pdf | Progress Report | Public |
Quarterly Report: 6-30-2006 | qtrly_rpt_06-30-06.pdf | Progress Report | Public |
Quarterly Report: 3-31-2006 | qtrly_rpt_03-31-06.pdf | Progress Report | Public |
Quarterly Report: 12-31-2005 | qtrly_rpt_12-31-05.pdf | Progress Report | Public |
Quarterly Report: 9-30-2005 | qtrly_rpt_09-30-05.pdf | Progress Report | Public |
Quarterly Report: 6-30-2005 | qtrly_rpt_06-30-05.pdf | Progress Report | Public |
Quarterly Report: 3-31-2005 | qtrly_rpt_03-31-05.pdf | Progress Report | Public |
Agreement and Proposal | work_plan_09-09-02.pdf | TPF Study Documentation | Public |
Quarterly Report: 12-31-2002 | qtrly_rpt_12-31-02.pdf | Progress Report | Public |
Quarterly Report: 3-31-2003 | qtrly_rpt_03-31-03.pdf | Progress Report | Public |
Quarterly Report: 6-30-2003 | qtrly_rpt_06-30-03.pdf | Progress Report | Public |
Quarterly Report: 9-30-2003 | qtrly_rpt_9-30-03.pdf | Progress Report | Public |
Quarterly Report: 12-31-2003 | qtrly_rpt_12-31-03.pdf | Progress Report | Public |
Quarterly Report: 3-31-2004 | qtrly_rpt_03-31-04.pdf | Progress Report | Public |
Quarterly Report: 6-30-2004 | qtrly_rpt_06-30-04.pdf | Progress Report | Public |
Quarterly Report: 9-30-2004 | qtrly_rpt_09-30-04.pdf | Progress Report | Public |
Quarterly Report: 12-31-2004 | qtrly_rpt_12-31-04.pdf | Progress Report | Public |