State Pavement Technology Consortium

Print
General Information
Study Number: SPR-3(074)
Former Study Number:
Lead Organization: Washington State Department of Transportation
Contract Start Date: Jan 25, 1999
Solicitation Number: 144
Partners: CA, MN, TX, WA
Contractor(s): University of Washington
Status: Closed
Est. Completion Date: Jul 31, 2015
Contract/Other Number:
Last Updated: Dec 13, 2017
Contract End Date: Jul 31, 2015
Financial Summary
Contract Amount: $40,000.00
Suggested Contribution:
Total Commitments Received: $355,000.00
100% SP&R Approval: Approved
Contact Information
Lead Study Contact(s): Mustafa Mohamedali
Mustafa.Mohamedali@wsdot.wa.gov
Phone: 360-704-6307
Organization Year Commitments Technical Contact Name Funding Contact Name
California Department of Transportation 2007 $0.00
Minnesota Department of Transportation 2006 $40,000.00 Maureen Jensen Lisa Jansen
Minnesota Department of Transportation 2007 $15,000.00 Maureen Jensen Lisa Jansen
Minnesota Department of Transportation 2009 $30,000.00 Maureen Jensen Lisa Jansen
Minnesota Department of Transportation 2010 $15,000.00 Maureen Jensen Lisa Jansen
Minnesota Department of Transportation 2011 $15,000.00 Maureen Jensen Lisa Jansen
Minnesota Department of Transportation 2012 $15,000.00 Maureen Jensen Lisa Jansen
Texas Department of Transportation 2007 $15,000.00 Dale Rand Ned Mattila
Texas Department of Transportation 2008 $15,000.00 Dale Rand Ned Mattila
Texas Department of Transportation 2009 $15,000.00 Dale Rand Ned Mattila
Texas Department of Transportation 2010 $15,000.00 Dale Rand Ned Mattila
Texas Department of Transportation 2011 $15,000.00 Dale Rand Ned Mattila
Washington State Department of Transportation 2005 $60,000.00 Linda Pierce Kim Willoughby
Washington State Department of Transportation 2006 $15,000.00 Linda Pierce Kim Willoughby
Washington State Department of Transportation 2007 $15,000.00 Linda Pierce Kim Willoughby
Washington State Department of Transportation 2008 $15,000.00 Linda Pierce Kim Willoughby
Washington State Department of Transportation 2009 $15,000.00 Linda Pierce Kim Willoughby
Washington State Department of Transportation 2010 $15,000.00 Linda Pierce Kim Willoughby
Washington State Department of Transportation 2012 $15,000.00 Linda Pierce Kim Willoughby

Study Description

The SPTC has been active since 1999.

Objectives

The SPTC meets once a year to discuss technical issues plaguing the member states on pavements, materials and construction. We also perform research studies when necessary.

Subjects: Maintenance Materials and Construction Pavement Design, Management, and Performance

Documents Attached
Title File/Link Document Category Document Type Privacy Document Date Download
SPR-3(074) Closeout Letter SPR-3(074) Closeout Letter - Signed.pdf Memorandum Other Public 2017-12-19
SPR-3(074) FMIS Data for Closeout SPR-3(074) FMIS Data for Closeout 9-05-2017-Sorensen.pdf Other Other Public 2017-12-13
SPR-3(074) Closeout Funding Spreadsheet SPR-3(074) Closeout Funding Spreadsheet - Sorensen-Oman.xls Other Other Public 2017-12-13
Report 840.2 WA-RD 840.2.pdf Deliverable Final Report Public 2016-04-29
Report 840.1 WA-RD 840.1.pdf Deliverable Final Report Public 2016-04-29
1/1/16-3/31/16 SPR-3(074) 1st Quarter 2016.docx Progress Report Quarterly Progress Report Public 2016-04-29
1/1/15 -3/31/15 SPR-3(074) 1st Quarter 2015.docx Progress Report Quarterly Progress Report Public 2015-04-07
7/1/14-9/30/14 SPR-3(074) 3rd Quarter 2014.docx Progress Report Quarterly Progress Report Public 2014-12-17
4/1/14-6/30/14 SPR-3(074) 2nd Quarter 2014.docx Progress Report Quarterly Progress Report Public 2014-09-17
10/1/13-12/31/14 SPR-3(074) 4th Quarter 2013.docx Progress Report Quarterly Progress Report Public 2014-01-30
7/1/13-9/30/13 SPR-3(074) 3rd Quarter 2013.docx Progress Report Quarterly Progress Report Public 2013-10-30
4/1/13-6/30/13 SPR-3(074) 2nd Quarter 2013.docx Progress Report Quarterly Progress Report Public 2013-08-21
1/1/13-3/31/13 SPR-3(074) 1st Quarter 2013.docx Progress Report Quarterly Progress Report Public 2013-05-29
10/1/12-12/31/12 SPR-3(074) 4th Quarter 2012.docx Progress Report Quarterly Progress Report Public 2013-01-15
7/1/12-9/30/12 SPR-3(074) 3rd Quarter 2012.docx Progress Report Quarterly Progress Report Public 2012-10-31
4/1/12-6/30/12 SPR-3(074) 2nd Quarter 2012.docx Progress Report Quarterly Progress Report Public 2012-09-20
1/1/12-3/31/12 SPR-3(074) 1st Quarter 2012.docx Progress Report Quarterly Progress Report Public 2012-03-27
10/1/11-12/31/11 SPR-3(074) 4th Quarter 2011.docx Progress Report Quarterly Progress Report Public 2012-02-22
July 1, 2011 - September 30, 2011 SPR-3(074) 3rd Quarter 2011.doc Progress Report Quarterly Progress Report Public 2011-10-14
April 1, 2011 - June 30, 2011 SPR-3(074)_2nd_Quarter_2011.pdf Progress Report Quarterly Progress Report Public 2011-07-19
April 1, 2008 - June 30, 2008 quarterly_report_06-30-08.pdf Progress Report Quarterly Progress Report Public 2008-08-05
January 1, 2011 through March 31, 2011 SPR-3(074) 1st Quarter 2011.pdf Progress Report Quarterly Progress Report Public 2011-05-31
April 1, 2010 - June 30, 2010 SPR-3(074)_2nd_Quarter_2010.pdf Progress Report Quarterly Progress Report Public 2010-08-06
January 1, 2010 - March 31, 2010 SPR-3(074)_1st_Quarter_2010.pdf Progress Report Quarterly Progress Report Public 2010-05-06
October 1, 2009 - December 31, 2009 quarterly_report_12-31-09.pdf Progress Report Quarterly Progress Report Public 2010-01-13
April 1, 2009 - June 30, 2009 quarterly_report_06-30-09.pdf Progress Report Quarterly Progress Report Public 2009-09-02
October 1, 2008 - December 31, 2008 quarterly_report_12-31-08.pdf Progress Report Quarterly Progress Report Public 2009-02-13
January 1, 2009 - March 31, 2009 quarterly_report_03-31-09.pdf Progress Report Quarterly Progress Report Public 2009-06-09
January 1, 2008 - March 31, 2008 quarterly_report_03-31-08.pdf Progress Report Quarterly Progress Report Public 2008-05-06
July 1, 2006 - September 30, 2006 quarterly_report_09-30-06.pdf Progress Report Quarterly Progress Report Public 2006-10-25
July 1, 2007 - September 30, 2007 quarterly_report_09-30-07.pdf Progress Report Quarterly Progress Report Public 2007-11-02
April 1, 2007 - June 30, 2007 quarterly_report_06-30-07.pdf Progress Report Quarterly Progress Report Public 2007-07-13
January 1, 2007 - March 31, 2007 quarterly_report_03-31-07.pdf Progress Report Quarterly Progress Report Public 2007-04-25
October 1, 2006 - December 31, 2006 quarterly_report_12-31-06.pdf Progress Report Quarterly Progress Report Public 2007-02-08
January 1, 2006 - March 31, 2006 quarterly_report_03-31-06.pdf Progress Report Quarterly Progress Report Public 2006-05-03
October 1, 2005 - December 31, 2005 quarterly_report_12-31-05.pdf Progress Report Quarterly Progress Report Public 2006-02-07
July 1, 2005 - September 30, 2005 quarterly_report_09-30-05.pdf Progress Report Quarterly Progress Report Public 2005-10-25
April 1, 2006 - June 30, 2006 quarterly_report_06-30-06.pdf Progress Report Quarterly Progress Report Public 2006-07-18
Modified_Tack_Coat_Proposal-July_26_2005 Modified_Tack_Coat_Proposal-July_26_2005.pdf Other Other Public 2005-07-28
April 1, 2005 - June 30, 2005 qrtrly_rpt_06-30-05.pdf Progress Report Quarterly Progress Report Public 2005-07-14
Pooled Fund Project Status Report quarterly_report_12-31-02.pdf Progress Report Quarterly Progress Report Public 2004-11-15
July 1, 2003 - September 30, 2003 quarterly_report_09-30-03.pdf Progress Report Quarterly Progress Report Public 2004-11-15
January 1, 2004 - March 31, 2004 qtrly_rept_03-31-04.pdf Progress Report Quarterly Progress Report Public 2004-11-15
January 1, 2004 - June 30, 2004 quarterly_report_06-30-04.pdf Progress Report Quarterly Progress Report Public 2004-11-15
July 1, 2004 through December 31, 2004 quarterly_report_12-31-04.pdf Progress Report Quarterly Progress Report Public 2004-11-15
January 1, 2005 through March 31, 2005 quarterly_report_03-31-05.pdf Progress Report Quarterly Progress Report Public 2005-04-29

No document attached.

State Pavement Technology Consortium

General Information
Study Number: SPR-3(074)
Lead Organization: Washington State Department of Transportation
Contract Start Date: Jan 25, 1999
Solicitation Number: 144
Partners: CA, MN, TX, WA
Contractor(s): University of Washington
Status: Closed
Est. Completion Date: Jul 31, 2015
Contract/Other Number:
Last Updated: Dec 13, 2017
Contract End Date: Jul 31, 2015
Financial Summary
Contract Amount: $40,000.00
Total Commitments Received: $355,000.00
100% SP&R Approval:
Contact Information
Lead Study Contact(s): Mustafa Mohamedali
Mustafa.Mohamedali@wsdot.wa.gov
Phone: 360-704-6307
Commitments by Organizations
Organization Year Commitments Technical Contact Name Funding Contact Name Contact Number Email Address
California Department of Transportation 2007 $0.00
Minnesota Department of Transportation 2006 $40,000.00 Maureen Jensen Lisa Jansen 651-366-3779 lisa.jansen@state.mn.us
Minnesota Department of Transportation 2007 $15,000.00 Maureen Jensen Lisa Jansen 651-366-3779 lisa.jansen@state.mn.us
Minnesota Department of Transportation 2009 $30,000.00 Maureen Jensen Lisa Jansen 651-366-3779 lisa.jansen@state.mn.us
Minnesota Department of Transportation 2010 $15,000.00 Maureen Jensen Lisa Jansen 651-366-3779 lisa.jansen@state.mn.us
Minnesota Department of Transportation 2011 $15,000.00 Maureen Jensen Lisa Jansen 651-366-3779 lisa.jansen@state.mn.us
Minnesota Department of Transportation 2012 $15,000.00 Maureen Jensen Lisa Jansen 651-366-3779 lisa.jansen@state.mn.us
Texas Department of Transportation 2007 $15,000.00 Dale Rand Ned Mattila 512-416-4727 ned.mattila@txdot.gov
Texas Department of Transportation 2008 $15,000.00 Dale Rand Ned Mattila 512-416-4727 ned.mattila@txdot.gov
Texas Department of Transportation 2009 $15,000.00 Dale Rand Ned Mattila 512-416-4727 ned.mattila@txdot.gov
Texas Department of Transportation 2010 $15,000.00 Dale Rand Ned Mattila 512-416-4727 ned.mattila@txdot.gov
Texas Department of Transportation 2011 $15,000.00 Dale Rand Ned Mattila 512-416-4727 ned.mattila@txdot.gov
Washington State Department of Transportation 2005 $60,000.00 Linda Pierce Kim Willoughby 360-705-7978 willouk@wsdot.wa.gov
Washington State Department of Transportation 2006 $15,000.00 Linda Pierce Kim Willoughby 360-705-7978 willouk@wsdot.wa.gov
Washington State Department of Transportation 2007 $15,000.00 Linda Pierce Kim Willoughby 360-705-7978 willouk@wsdot.wa.gov
Washington State Department of Transportation 2008 $15,000.00 Linda Pierce Kim Willoughby 360-705-7978 willouk@wsdot.wa.gov
Washington State Department of Transportation 2009 $15,000.00 Linda Pierce Kim Willoughby 360-705-7978 willouk@wsdot.wa.gov
Washington State Department of Transportation 2010 $15,000.00 Linda Pierce Kim Willoughby 360-705-7978 willouk@wsdot.wa.gov
Washington State Department of Transportation 2012 $15,000.00 Linda Pierce Kim Willoughby 360-705-7978 willouk@wsdot.wa.gov

Study Description

Study Description

The SPTC has been active since 1999.

Objectives

The SPTC meets once a year to discuss technical issues plaguing the member states on pavements, materials and construction. We also perform research studies when necessary.

Subjects: Maintenance Materials and Construction Pavement Design, Management, and Performance

Title File/Link Type Private
SPR-3(074) Closeout Letter SPR-3(074) Closeout Letter - Signed.pdf Memorandum Public
SPR-3(074) FMIS Data for Closeout SPR-3(074) FMIS Data for Closeout 9-05-2017-Sorensen.pdf Other Public
SPR-3(074) Closeout Funding Spreadsheet SPR-3(074) Closeout Funding Spreadsheet - Sorensen-Oman.xls Other Public
Report 840.2 WA-RD 840.2.pdf Deliverable Public
Report 840.1 WA-RD 840.1.pdf Deliverable Public
1/1/16-3/31/16 SPR-3(074) 1st Quarter 2016.docx Progress Report Public
1/1/15 -3/31/15 SPR-3(074) 1st Quarter 2015.docx Progress Report Public
7/1/14-9/30/14 SPR-3(074) 3rd Quarter 2014.docx Progress Report Public
4/1/14-6/30/14 SPR-3(074) 2nd Quarter 2014.docx Progress Report Public
10/1/13-12/31/14 SPR-3(074) 4th Quarter 2013.docx Progress Report Public
7/1/13-9/30/13 SPR-3(074) 3rd Quarter 2013.docx Progress Report Public
4/1/13-6/30/13 SPR-3(074) 2nd Quarter 2013.docx Progress Report Public
1/1/13-3/31/13 SPR-3(074) 1st Quarter 2013.docx Progress Report Public
10/1/12-12/31/12 SPR-3(074) 4th Quarter 2012.docx Progress Report Public
7/1/12-9/30/12 SPR-3(074) 3rd Quarter 2012.docx Progress Report Public
4/1/12-6/30/12 SPR-3(074) 2nd Quarter 2012.docx Progress Report Public
1/1/12-3/31/12 SPR-3(074) 1st Quarter 2012.docx Progress Report Public
10/1/11-12/31/11 SPR-3(074) 4th Quarter 2011.docx Progress Report Public
July 1, 2011 - September 30, 2011 SPR-3(074) 3rd Quarter 2011.doc Progress Report Public
April 1, 2011 - June 30, 2011 SPR-3(074)_2nd_Quarter_2011.pdf Progress Report Public
January 1, 2011 through March 31, 2011 SPR-3(074) 1st Quarter 2011.pdf Progress Report Public
April 1, 2010 - June 30, 2010 SPR-3(074)_2nd_Quarter_2010.pdf Progress Report Public
January 1, 2010 - March 31, 2010 SPR-3(074)_1st_Quarter_2010.pdf Progress Report Public
October 1, 2009 - December 31, 2009 quarterly_report_12-31-09.pdf Progress Report Public
April 1, 2009 - June 30, 2009 quarterly_report_06-30-09.pdf Progress Report Public
January 1, 2009 - March 31, 2009 quarterly_report_03-31-09.pdf Progress Report Public
October 1, 2008 - December 31, 2008 quarterly_report_12-31-08.pdf Progress Report Public
April 1, 2008 - June 30, 2008 quarterly_report_06-30-08.pdf Progress Report Public
January 1, 2008 - March 31, 2008 quarterly_report_03-31-08.pdf Progress Report Public
July 1, 2007 - September 30, 2007 quarterly_report_09-30-07.pdf Progress Report Public
April 1, 2007 - June 30, 2007 quarterly_report_06-30-07.pdf Progress Report Public
January 1, 2007 - March 31, 2007 quarterly_report_03-31-07.pdf Progress Report Public
October 1, 2006 - December 31, 2006 quarterly_report_12-31-06.pdf Progress Report Public
July 1, 2006 - September 30, 2006 quarterly_report_09-30-06.pdf Progress Report Public
April 1, 2006 - June 30, 2006 quarterly_report_06-30-06.pdf Progress Report Public
January 1, 2006 - March 31, 2006 quarterly_report_03-31-06.pdf Progress Report Public
October 1, 2005 - December 31, 2005 quarterly_report_12-31-05.pdf Progress Report Public
July 1, 2005 - September 30, 2005 quarterly_report_09-30-05.pdf Progress Report Public
Modified_Tack_Coat_Proposal-July_26_2005 Modified_Tack_Coat_Proposal-July_26_2005.pdf Other Public
April 1, 2005 - June 30, 2005 qrtrly_rpt_06-30-05.pdf Progress Report Public
January 1, 2005 through March 31, 2005 quarterly_report_03-31-05.pdf Progress Report Public
July 1, 2004 through December 31, 2004 quarterly_report_12-31-04.pdf Progress Report Public
January 1, 2004 - June 30, 2004 quarterly_report_06-30-04.pdf Progress Report Public
January 1, 2004 - March 31, 2004 qtrly_rept_03-31-04.pdf Progress Report Public
July 1, 2003 - September 30, 2003 quarterly_report_09-30-03.pdf Progress Report Public
Pooled Fund Project Status Report quarterly_report_12-31-02.pdf Progress Report Public
No document attached.

Currently, Transportation Pooled Fund is not supported on mobile devices, please access this Web portal using a desktop or laptop computer.