TEL8 Telecommunications System

Print
General Information
Study Number: SPR-3(099)
Former Study Number:
Lead Organization: North Dakota Department of Transportation
Solicitation Number: 136
Partners: CO, MT, ND, SD, UT, WY
Status: Closed
Est. Completion Date: Sep 30, 2015
Contract/Other Number:
Last Updated: May 25, 2016
Contract End Date: Sep 30, 2015
Financial Summary
Contract Amount: $0.00
Suggested Contribution:
Total Commitments Received: $989,000.00
100% SP&R Approval: Approved
Contact Information
Lead Study Contact(s): Clayton Schumaker
cschumaker@nd.gov
Phone: 701- 328-6906
FHWA Technical Liaison(s): Stephanie Hickman
stephanie.hickman@dot.gov
Phone: 701-221-9462
Study Champion(s): Gerri Weisgerber
gweisger@nd.gov
Phone: 701- 328-6901
Organization Year Commitments Technical Contact Name Funding Contact Name
Colorado Department of Transportation 0 $0.00
Montana Department of Transportation 0 $0.00 Brad Nelson Susan Sillick
Montana Department of Transportation 2013 $117,000.00 Brad Nelson Susan Sillick
Montana Department of Transportation 2014 $117,000.00 Brad Nelson Susan Sillick
Montana Department of Transportation 2015 $117,000.00 Brad Nelson Susan Sillick
North Dakota Department of Transportation 0 $117,000.00 Clayton Schumaker Clayton Schumaker
North Dakota Department of Transportation 1 $117,000.00 Clayton Schumaker Clayton Schumaker
North Dakota Department of Transportation 2 $117,000.00 Clayton Schumaker Clayton Schumaker
South Dakota Department of Transportation 0 $117,000.00 David Huft David Huft
South Dakota Department of Transportation 2 $170,000.00 David Huft David Huft
Utah Department of Transportation 0 $0.00 Daniel Hsiao
Wyoming Department of Transportation 0 $0.00

Objectives

Distance learning including graduate-level courses in transportation; technology transfer and continuing education in transportation subjects; seminars and information exchanges; uplinks to national transportation events and information exchanges. See http://www.tel8.org/ for more details.

Comments

Ongoing. Project began in mid-2000. 2/14/02

Subjects: Planning and Administration

Documents Attached
Title File/Link Document Category Document Type Privacy Document Date Download
SPR-3(099) Closeout Letter SPR-3(099) Close out Memo - Signed.pdf Memorandum Other Public 2016-05-25
SPR-3(099) Closeout Funding Spreadsheet SPR-3(099) Closeout Funding Spreadsheet.pdf Other Other Public 2016-05-25
TLN Final Report TEL8 TELECOMMUNICATIONS NETWORK Final Report.docx Deliverable Final Report Public 2016-03-10
3rd Quarter Report: July 1, 2015 to September 30, 2015 TLN Qtrly (July-Sept 2015) Progress Rpt.pdf Progress Report Quarterly Progress Report Public 2015-12-29
2nd Quarter Report: April - June 2015 TLN Qtrly (APR-JUNE 2015) Progress Rpt .pdf Progress Report Quarterly Progress Report Public 2015-07-20
Interim Report July 1, 2013 to June 30, 2015 TLN Interim Report_May-2015.pdf TPF Study Documentation Research Report Public 2015-05-31
1st Quarter Report: January 1 - March 31, 2015 TLN Qtrly (JAN-MAR 2015) Progress Rpt .pdf Progress Report Quarterly Progress Report Public 2015-06-05
4th Quarter Report: October - December 2014 TLN Qtrly (Oct-Dec 2014) Progress Rpt .pdf Progress Report Quarterly Progress Report Public 2015-06-04
3rd Quarterly Report: July 1 - September 30, 2014 TLN Qtrly (July-Sept 2014) Progress Rpt .pdf Progress Report Quarterly Progress Report Public 2015-03-26
Quarterly Report: April - June 2014 TLN Qtrly (Apr - June 2014) Progress Rpt .docx Progress Report Quarterly Progress Report Public 2014-07-15
1st Quarter Report: January - March 2014 TLN Qtrly (Jan - Mar 2014) Progress Rpt .docx Progress Report Quarterly Progress Report Public 2014-05-14
4th Quarter Report: October - December 2013 TLN Qtrly (Oct - Dec 2013) Progress Rpt .docx Progress Report Quarterly Progress Report Public 2014-05-14
3rd Quarter Report: July - September 2013 TLN Qtrly (July-Sept 2013) Progress Rpt .docx Progress Report Quarterly Progress Report Public 2013-11-04
1st Quarter Report: January - March 2013 TLN Qtrly (Jan - Mar 2013) Progress Rpt .docx Progress Report Quarterly Progress Report Public 2013-05-09
4th Quarter Report: October - December 2012 TLN Qtrly (Oct - Dec 2012) Progress Rpt .docx Progress Report Quarterly Progress Report Public 2013-05-09
3rd Quarter Report: July - September 2012 Quarter 3 (Jul-Sept 2012).pdf Progress Report Quarterly Progress Report Public 2012-11-01
Quarterly Report: April - June 2012 (Revised) TLN Qtrly (Apr-June 2012) Progress Rpt .docx Progress Report Quarterly Progress Report Public 2012-08-14
Quarterly Report: January - March 2012 TLN Qtrly (Jan-Mar 2012) Progress Rpt .pdf Progress Report Quarterly Progress Report Public 2012-05-07
Quartely Report: October - December 2011 TLN Qtrly (Oct-Dec 2011) Progress Rpt.pdf Progress Report Quarterly Progress Report Public 2012-05-07
Quarterly Report: July-September 2011 SPR-3(099) QTR 3 Pooled Fund Report July-Sept 2011.docx Progress Report Quarterly Progress Report Public 2011-11-04
Quarterly Report: April - June 2011 QTR_2_Pooled_Fund_Report_2010-2011.pdf Progress Report Quarterly Progress Report Public 2011-07-25
Quarterly Report: October - December 2010 QTR 4 Pooled Fund Report 2010-2011.pdf Progress Report Quarterly Progress Report Public 2011-07-06
Quarterly Report: January - March 2011 QTR 1 Pooled Fund Report 2010-2011.pdf Progress Report Quarterly Progress Report Public 2011-07-06
Quarterly Report: January - March 2010 Qtr 3 Jan-Mar 2010.pdf Progress Report Quarterly Progress Report Public 2011-05-20
Quarterly Report: April - June 2009 Qtr4_2009_April-June.pdf Progress Report Quarterly Progress Report Public 2010-01-04
Quarterly Report: January - March 2009 Qtr3_2009_Jan-March.pdf Progress Report Quarterly Progress Report Public 2010-01-04
Quarterly Report: April - June 2007 Quarterly_Report_2007_06_30.pdf Progress Report Quarterly Progress Report Public 2007-10-03
Quarterly Report: October - December 2005 Quarterly_Report_2005_12_31.pdf Progress Report Quarterly Progress Report Public 2006-08-17
Annual Report: 2002 - 2003 annual_report_02-03.pdf Progress Report Annual Report Public 2004-05-07

No document attached.

TEL8 Telecommunications System

General Information
Study Number: SPR-3(099)
Lead Organization: North Dakota Department of Transportation
Solicitation Number: 136
Partners: CO, MT, ND, SD, UT, WY
Status: Closed
Est. Completion Date: Sep 30, 2015
Contract/Other Number:
Last Updated: May 25, 2016
Contract End Date: Sep 30, 2015
Financial Summary
Contract Amount: $0.00
Total Commitments Received: $989,000.00
100% SP&R Approval:
Contact Information
Lead Study Contact(s): Clayton Schumaker
cschumaker@nd.gov
Phone: 701- 328-6906
FHWA Technical Liaison(s): Stephanie Hickman
stephanie.hickman@dot.gov
Phone: 701-221-9462
Commitments by Organizations
Organization Year Commitments Technical Contact Name Funding Contact Name Contact Number Email Address
Colorado Department of Transportation 0 $0.00
Montana Department of Transportation 0 $0.00 Brad Nelson Susan Sillick 406-444-7693 ssillick@mt.gov
Montana Department of Transportation 2013 $117,000.00 Brad Nelson Susan Sillick 406-444-7693 ssillick@mt.gov
Montana Department of Transportation 2014 $117,000.00 Brad Nelson Susan Sillick 406-444-7693 ssillick@mt.gov
Montana Department of Transportation 2015 $117,000.00 Brad Nelson Susan Sillick 406-444-7693 ssillick@mt.gov
North Dakota Department of Transportation 0 $117,000.00 Clayton Schumaker Clayton Schumaker 701- 328-6906 cschumaker@nd.gov
North Dakota Department of Transportation 1 $117,000.00 Clayton Schumaker Clayton Schumaker 701- 328-6906 cschumaker@nd.gov
North Dakota Department of Transportation 2 $117,000.00 Clayton Schumaker Clayton Schumaker 701- 328-6906 cschumaker@nd.gov
South Dakota Department of Transportation 0 $117,000.00 David Huft David Huft 605-773-3358 dave.huft@state.sd.us
South Dakota Department of Transportation 2 $170,000.00 David Huft David Huft 605-773-3358 dave.huft@state.sd.us
Utah Department of Transportation 0 $0.00 Daniel Hsiao 801-386-4929 dhsiao@utah.gov
Wyoming Department of Transportation 0 $0.00

Study Description

Objectives

Distance learning including graduate-level courses in transportation; technology transfer and continuing education in transportation subjects; seminars and information exchanges; uplinks to national transportation events and information exchanges. See http://www.tel8.org/ for more details.

Comments

Ongoing. Project began in mid-2000. 2/14/02

Subjects: Planning and Administration

Title File/Link Type Private
SPR-3(099) Closeout Letter SPR-3(099) Close out Memo - Signed.pdf Memorandum Public
SPR-3(099) Closeout Funding Spreadsheet SPR-3(099) Closeout Funding Spreadsheet.pdf Other Public
TLN Final Report TEL8 TELECOMMUNICATIONS NETWORK Final Report.docx Deliverable Public
3rd Quarter Report: July 1, 2015 to September 30, 2015 TLN Qtrly (July-Sept 2015) Progress Rpt.pdf Progress Report Public
2nd Quarter Report: April - June 2015 TLN Qtrly (APR-JUNE 2015) Progress Rpt .pdf Progress Report Public
1st Quarter Report: January 1 - March 31, 2015 TLN Qtrly (JAN-MAR 2015) Progress Rpt .pdf Progress Report Public
4th Quarter Report: October - December 2014 TLN Qtrly (Oct-Dec 2014) Progress Rpt .pdf Progress Report Public
Interim Report July 1, 2013 to June 30, 2015 TLN Interim Report_May-2015.pdf TPF Study Documentation Public
3rd Quarterly Report: July 1 - September 30, 2014 TLN Qtrly (July-Sept 2014) Progress Rpt .pdf Progress Report Public
Quarterly Report: April - June 2014 TLN Qtrly (Apr - June 2014) Progress Rpt .docx Progress Report Public
4th Quarter Report: October - December 2013 TLN Qtrly (Oct - Dec 2013) Progress Rpt .docx Progress Report Public
1st Quarter Report: January - March 2014 TLN Qtrly (Jan - Mar 2014) Progress Rpt .docx Progress Report Public
3rd Quarter Report: July - September 2013 TLN Qtrly (July-Sept 2013) Progress Rpt .docx Progress Report Public
4th Quarter Report: October - December 2012 TLN Qtrly (Oct - Dec 2012) Progress Rpt .docx Progress Report Public
1st Quarter Report: January - March 2013 TLN Qtrly (Jan - Mar 2013) Progress Rpt .docx Progress Report Public
3rd Quarter Report: July - September 2012 Quarter 3 (Jul-Sept 2012).pdf Progress Report Public
Quarterly Report: April - June 2012 (Revised) TLN Qtrly (Apr-June 2012) Progress Rpt .docx Progress Report Public
Quarterly Report: January - March 2012 TLN Qtrly (Jan-Mar 2012) Progress Rpt .pdf Progress Report Public
Quartely Report: October - December 2011 TLN Qtrly (Oct-Dec 2011) Progress Rpt.pdf Progress Report Public
Quarterly Report: July-September 2011 SPR-3(099) QTR 3 Pooled Fund Report July-Sept 2011.docx Progress Report Public
Quarterly Report: April - June 2011 QTR_2_Pooled_Fund_Report_2010-2011.pdf Progress Report Public
Quarterly Report: January - March 2011 QTR 1 Pooled Fund Report 2010-2011.pdf Progress Report Public
Quarterly Report: October - December 2010 QTR 4 Pooled Fund Report 2010-2011.pdf Progress Report Public
Quarterly Report: January - March 2010 Qtr 3 Jan-Mar 2010.pdf Progress Report Public
Quarterly Report: January - March 2009 Qtr3_2009_Jan-March.pdf Progress Report Public
Quarterly Report: April - June 2009 Qtr4_2009_April-June.pdf Progress Report Public
Quarterly Report: April - June 2007 Quarterly_Report_2007_06_30.pdf Progress Report Public
Quarterly Report: October - December 2005 Quarterly_Report_2005_12_31.pdf Progress Report Public
Annual Report: 2002 - 2003 annual_report_02-03.pdf Progress Report Public
No document attached.

Currently, Transportation Pooled Fund is not supported on mobile devices, please access this Web portal using a desktop or laptop computer.