Financial Summary |
|
Suggested Contribution: | |
Commitment Start Year: | 1993 |
Commitment End Year: | 1996 |
100% SP&R Approval: | Not Requested |
Commitments Required: | |
Commitments Received: | $177,000.00 |
Estimated Duration Month: | |
Waiver Requested: | No |
Contact Information |
|
Lead Study Contact(s): | Jean Landolt |
Jean.Landolt@dot.gov | |
FHWA Technical Liaison(s): | John O'Fallon |
john.o’fallon@dot.gov | |
Phone: 202-493-3051 |
Organization | Year | Commitments | Technical Contact Name | Funding Contact Name | Contact Number | Email Address |
---|---|---|---|---|---|---|
California Department of Transportation | 1993 | $15,000.00 | Rod Prysock | Tim Leahy | 916-739-5792 | tim.leahy@dot.ca.gov |
California Department of Transportation | 1994 | $15,000.00 | Rod Prysock | Tim Leahy | 916-739-5792 | tim.leahy@dot.ca.gov |
California Department of Transportation | 1995 | $15,000.00 | Rod Prysock | Tim Leahy | 916-739-5792 | tim.leahy@dot.ca.gov |
Federal Highway Administration | 1993 | $10,000.00 | Alfred Logie | 703-404-6201 | ||
Iowa Department of Transportation | 1993 | $1,500.00 | Kermit Dirks | Steve Kadolph | 515-239-1677 | steven.kadolph@iowadot.us |
Iowa Department of Transportation | 1994 | $1,500.00 | Kermit Dirks | Steve Kadolph | 515-239-1677 | steven.kadolph@iowadot.us |
Kansas Department of Transportation | 1993 | $3,000.00 | James Brennan | James Brennan | 785-296-3524 | James.Brennan@ks.gov |
Kansas Department of Transportation | 1994 | $3,000.00 | James Brennan | James Brennan | 785-296-3524 | James.Brennan@ks.gov |
Louisiana Department of Transportation and Development | 1994 | $5,000.00 | Paul Griffin, Jr. | Al Dunn | 225-379-1234 | al.dunn@la.gov |
Massachusetts Department of Transportation | 1993 | $7,500.00 | Nabil Hourani | Walter Kondo | 617-973-7800 | |
Massachusetts Department of Transportation | 1994 | $7,500.00 | Nabil Hourani | Walter Kondo | 617-973-7800 | |
Massachusetts Executive Office of Transportation and Construction | 1993 | $0.00 | ||||
Minnesota Department of Transportation | 1993 | $20,000.00 | Don Flemming | Don Flemming | 651-296-3172 | |
New York State Department of Transportation | 1993 | $5,000.00 | Edward Fernau | Edward Fernau | 518-457-4719 | |
New York State Department of Transportation | 1994 | $5,000.00 | Edward Fernau | Edward Fernau | 518-457-4719 | |
Ohio Department of Transportation | 1993 | $3,000.00 | John Hurd | John Hurd | 614-466-3348 | |
Ohio Department of Transportation | 1994 | $10,000.00 | John Hurd | John Hurd | 614-466-3348 | |
Oklahoma Transportation | 1993 | $5,000.00 | Veldo Goins | C. Hixon | 405-521-2671 | |
Oklahoma Transportation | 1994 | $5,000.00 | Veldo Goins | C. Hixon | 405-521-2671 | |
Pennsylvania Department of Transportation | 1993 | $15,000.00 | Steven Davis | Steven Davis | 717-787-1368 | |
Pennsylvania Department of Transportation | 1994 | $15,000.00 | Steven Davis | Steven Davis | 717-787-1368 | |
Wisconsin Department of Transportation | 1993 | $5,000.00 | Arnold Mohlman | Arnold Mohlman | 608-246-7909 | |
Wisconsin Department of Transportation | 1994 | $5,000.00 | Arnold Mohlman | Arnold Mohlman | 608-246-7909 |
To evaluate the interaction between culvert pipes, backfill envelopes, and in situ soil, and to develop recommended specification of installation of pipes to AASHTO standards.
The final report has been published as Pipe Interaction with the Backfill Envelope (FHWA-98-191). The report is available in PDF Format: Chapters 1-3, Chapter 4, Chapters 5-7, Appendix and Bibliography, The final draft of the proposed revisions to the LRFD Specification is being submitted and will be reviewed in-house, and then sent to the Culvert Research Advisory Committee for their review.
No document attached.
General Information |
|
Solicitation Number: | 71 |
Status: | End Solicitation Phase |
Date Posted: | Jul 01, 2002 |
Last Updated: | Mar 03, 2005 |
Solicitation Expires: | |
Partners: | CA, FHWA, IADOT, KS, LA, MA, MA, MN, NY, OH, OK, PADOT, WI |
Lead Organization: | Federal Highway Administration |
Financial Summary |
|
Suggested Contribution: | |
Commitment Start Year: | 1993 |
Commitment End Year: | 1996 |
100% SP&R Approval: | Not Requested |
Commitments Required: | |
Commitments Received: | $177,000.00 |
Contact Information |
|
Lead Study Contact(s): | Jean Landolt |
Jean.Landolt@dot.gov | |
FHWA Technical Liaison(s): | John O'Fallon |
john.o’fallon@dot.gov | |
Phone: 202-493-3051 |
Agency | Year | Commitments | Technical Contact Name | Funding Contact Name | Contact Number | Email Address |
---|---|---|---|---|---|---|
California Department of Transportation | 1993 | $15,000.00 | Rod Prysock | Tim Leahy | 916-739-5792 | tim.leahy@dot.ca.gov |
California Department of Transportation | 1994 | $15,000.00 | Rod Prysock | Tim Leahy | 916-739-5792 | tim.leahy@dot.ca.gov |
California Department of Transportation | 1995 | $15,000.00 | Rod Prysock | Tim Leahy | 916-739-5792 | tim.leahy@dot.ca.gov |
Federal Highway Administration | 1993 | $10,000.00 | Alfred Logie | 703-404-6201 | ||
Iowa Department of Transportation | 1993 | $1,500.00 | Kermit Dirks | Steve Kadolph | 515-239-1677 | steven.kadolph@iowadot.us |
Iowa Department of Transportation | 1994 | $1,500.00 | Kermit Dirks | Steve Kadolph | 515-239-1677 | steven.kadolph@iowadot.us |
Kansas Department of Transportation | 1993 | $3,000.00 | James Brennan | James Brennan | 785-296-3524 | James.Brennan@ks.gov |
Kansas Department of Transportation | 1994 | $3,000.00 | James Brennan | James Brennan | 785-296-3524 | James.Brennan@ks.gov |
Louisiana Department of Transportation and Development | 1994 | $5,000.00 | Paul Griffin, Jr. | Al Dunn | 225-379-1234 | al.dunn@la.gov |
Massachusetts Department of Transportation | 1993 | $7,500.00 | Nabil Hourani | Walter Kondo | 617-973-7800 | |
Massachusetts Department of Transportation | 1994 | $7,500.00 | Nabil Hourani | Walter Kondo | 617-973-7800 | |
Massachusetts Executive Office of Transportation and Construction | 1993 | $0.00 | ||||
Minnesota Department of Transportation | 1993 | $20,000.00 | Don Flemming | Don Flemming | 651-296-3172 | |
New York State Department of Transportation | 1993 | $5,000.00 | Edward Fernau | Edward Fernau | 518-457-4719 | |
New York State Department of Transportation | 1994 | $5,000.00 | Edward Fernau | Edward Fernau | 518-457-4719 | |
Ohio Department of Transportation | 1993 | $3,000.00 | John Hurd | John Hurd | 614-466-3348 | |
Ohio Department of Transportation | 1994 | $10,000.00 | John Hurd | John Hurd | 614-466-3348 | |
Oklahoma Transportation | 1993 | $5,000.00 | Veldo Goins | C. Hixon | 405-521-2671 | |
Oklahoma Transportation | 1994 | $5,000.00 | Veldo Goins | C. Hixon | 405-521-2671 | |
Pennsylvania Department of Transportation | 1993 | $15,000.00 | Steven Davis | Steven Davis | 717-787-1368 | |
Pennsylvania Department of Transportation | 1994 | $15,000.00 | Steven Davis | Steven Davis | 717-787-1368 | |
Wisconsin Department of Transportation | 1993 | $5,000.00 | Arnold Mohlman | Arnold Mohlman | 608-246-7909 | |
Wisconsin Department of Transportation | 1994 | $5,000.00 | Arnold Mohlman | Arnold Mohlman | 608-246-7909 |
To evaluate the interaction between culvert pipes, backfill envelopes, and in situ soil, and to develop recommended specification of installation of pipes to AASHTO standards.
The final report has been published as Pipe Interaction with the Backfill Envelope (FHWA-98-191). The report is available in PDF Format: Chapters 1-3, Chapter 4, Chapters 5-7, Appendix and Bibliography, The final draft of the proposed revisions to the LRFD Specification is being submitted and will be reviewed in-house, and then sent to the Culvert Research Advisory Committee for their review.