Midwest States Accelerated Testing

Print
General Information
Study Number: TPF-5(048)
Former Study Number:
Lead Organization: Kansas Department of Transportation
Contract Start Date: Jul 01, 2002
Solicitation Number: 812
Partners: IADOT, KS, MO, NE, NY
Contractor(s): Kansas State University
Status: Closed
Est. Completion Date: Jun 30, 2016
Contract/Other Number:
Last Updated: Dec 08, 2017
Contract End Date: Jun 30, 2016
Financial Summary
Contract Amount: $1,937,097.00
Suggested Contribution:
Total Commitments Received: $1,718,772.00
100% SP&R Approval: Approved
Contact Information
Lead Study Contact(s): Rodney Montney
rodney@ksdot.org
Phone: 785-291-3844
Organization Year Commitments Technical Contact Name Funding Contact Name
Iowa Department of Transportation 2003 $66,826.00 Scott Schram -- --
Iowa Department of Transportation 2004 $71,658.00 Scott Schram -- --
Iowa Department of Transportation 2005 $101,582.00 Scott Schram -- --
Iowa Department of Transportation 2006 $79,929.00 Scott Schram -- --
Iowa Department of Transportation 2007 $79,929.00 Scott Schram -- --
Kansas Department of Transportation 2003 $66,826.00 Andrew Gisi Rodney Montney
Kansas Department of Transportation 2004 $71,658.00 Andrew Gisi Rodney Montney
Kansas Department of Transportation 2005 $101,582.00 Andrew Gisi Rodney Montney
Kansas Department of Transportation 2006 $79,929.00 Andrew Gisi Rodney Montney
Kansas Department of Transportation 2007 $79,929.00 Andrew Gisi Rodney Montney
Kansas Department of Transportation 2008 $72,000.00 Andrew Gisi Rodney Montney
Kansas Department of Transportation 2009 $100,000.00 Andrew Gisi Rodney Montney
Missouri Department of Transportation 2003 $66,826.00 John Donahue Karmen Stockman
Missouri Department of Transportation 2004 $71,658.00 John Donahue Karmen Stockman
Missouri Department of Transportation 2005 $101,582.00 John Donahue Karmen Stockman
Missouri Department of Transportation 2006 $79,929.00 John Donahue Karmen Stockman
Missouri Department of Transportation 2007 $79,929.00 John Donahue Karmen Stockman
Missouri Department of Transportation 2008 $72,000.00 John Donahue Karmen Stockman
Missouri Department of Transportation 2009 $50,000.00 John Donahue Karmen Stockman
Nebraska Department of Transportation 2003 $55,000.00 George Woolstrum Amy Starr
Nebraska Department of Transportation 2004 $55,000.00 George Woolstrum Amy Starr
Nebraska Department of Transportation 2005 $55,000.00 George Woolstrum Amy Starr
New York State Department of Transportation 2009 $30,000.00 Bob Burnett Gary Frederick
New York State Department of Transportation 2010 $30,000.00 Bob Burnett Gary Frederick

Study Description

This is an ongoing project that has an annual program determined by the TAC.

Objectives

To evaluate various pavement components such as bases, ACP and PCCP using full scale accelerated pavement testing as determined by the TAC.

Scope of Work

Each annual work program has a specific scope of work. See attached proposals for details.

Comments

We are soliciting new partners for experiment no. 17 titled "Well Bonded Superpave Overlays on HMA". This experiment will involve a Laboratory phase and an Accelerated Pavement Testing phase that will run concurrently. The Laboratory testing will evaluate bond strength using a "Pull Off" test similar to ACI 503R, Appendix A, and a special test set up for shear. The APT phase will apply 500,000 passes of an 18-kip single axle load (dual tire) to six test sections. Test sections will be constructed using two different tack materials at 3 different tack application rates. All sections will consist of a 1-1/2" Superpave overlay placed over a 2-1/2" milled surface. Cost of experiment is approximately $135,000. We are requesting commitments of approximately $27,000 each from four additional partners to fund this experiment.

Subjects: Pavement Design, Management, and Performance

Documents Attached
Title File/Link Type Privacy Download
TPF-5(048) Closeout Letter TPF-5(048) Closeout Letter - Signed.pdf Memorandum Public
TPF-5(048) Closeout Funding Spreadsheet TPF-5(048) Closoeut Funding Spreadsheet.pdf Other Public
Midwest States Accelerated Testing Program Well Bonded Superpave Overlays on Hot Mix Asphalt Summary Report Midwest States Accelerated Testing Prog_Final Report Summary.pdf Other Public
Midwest States Accelerated Testing Program Well Bonded Superpave Overlays on Hot Mix Asphalt Final REport Midwest States Accelerated Testing Program_FinalReport.pdf Final Report Public
Quarterly Report Jan 2017 SPR_quarterly_report_TPF-5(048)_12-31-16 (2).pdf Quarterly Progress Report Public
Quarterly REport 2016 SPR_quarterly_report_TPF-5(048)_09-30-16.pdf Quarterly Progress Report Public
June 2016 Quarterly Report SPR_quarterly_report_TPF-5(048)_06-30-16.docx Quarterly Progress Report Public
Quarterly Report SPR_quarterly_report_TPF-5(048)_03-31-16.pdf Quarterly Progress Report Public
Quarterly Report Dec 2015 SPR_quarterly_report_TPF-5(048)_12-31-15.pdf Quarterly Progress Report Public
Quarterly Report Sept 2015 SPR_quarterly_report_TPF-5(048)_9-30-15 (2).pdf Quarterly Progress Report Public
Quarterly Report June 2015 SPR_quarterly_report_TPF-5(048)_6-30-15.pdf Quarterly Progress Report Public
Quarterly REport March 2015 SPR_quarterly_report_TPF-5(048)_3-31-15.pdf Quarterly Progress Report Public
Quarterly Report Dec 2014 SPR_quarterly_report_TPF-5(048) 12-31-14.pdf Quarterly Progress Report Public
Quarterly Report Sept 2014 SPR_quarterly_report_TPF-5(048) 09-30-14.pdf Quarterly Progress Report Public
Quarterly Report June 2014 SPR_quarterly_report_TPF-5(048) 06-30-14 (2).pdf Quarterly Progress Report Public
Quarterly REport March 2104 SPR_quarterly_report_TPF-5(048) 03-31-14 (2).pdf Quarterly Progress Report Public
Quarterly Report December 2013 SPR_quarterly_report_TPF-5(048) 12-31-13.pdf Quarterly Progress Report Public
Quarterly Report September 2013 SPR_quarterly_report_TPF-5(048) 09-30-13 (2).pdf Quarterly Progress Report Public
Quarterly Report June 2013 SPR_quarterly_report_TPF-5(048) 06-30-13 (2).pdf Quarterly Progress Report Public
Quarterly Report for perod ending 3/31/13 SPR_quarterly_report_TPF-5(048) 03-31-13.pdf Quarterly Progress Report Public
Sept 2012 Quarterly Report SPR_quarterly_report_TPF-5(048) 9-30-12.pdf Quarterly Progress Report Public
Quarterly Report June 2012 SPR_quarterly_report_TPF-5(048) 6-30-12.pdf Quarterly Progress Report Public
Quarterly Report for period ending 3/31/2012 SPR_quarterly_report_TPF-5(048) 3-31-12.pdf Quarterly Progress Report Public
Quarterly Report for period ending 12/31/2011 SPR_quarterly_report_TPF-5(048) 12-31-11.pdf Quarterly Progress Report Public
Quarterly Report for period ending 9/30/2011 SPR_quarterly_report_TPF-5(048) 9-30-11.pdf Quarterly Progress Report Public
Funding after conversion Sept 2011 TPF-5(048) Funding after conversion .pdf Other Public
Quarterly Progress Report for period ending 3/31/2011 SPR quarterly report TPF-5(048) 3-31-11.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2011 SPR_quarterly_report_TPF-5(048)_06-30-11.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2009 qtrly_rpt_2009-06-30.pdf Quarterly Progress Report Public
Quarterly Report: October 2010 - December 2010 SPRquarterlyreportTPF-5(048)12-31-10.pdf Quarterly Progress Report Public
Funding After Conversion TPF-5(048)Fundingafterconversion.xls Other Public
Quarterly Progress Report for period ending 03/31/2010 quarterly_report_03-31-10.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2010 SPR_quarterly_report_TPF-5(048)_06-30-10.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 9/30/2009 qtrly_rpt_2009-09-30.pdf Quarterly Progress Report Public
Funding Spreadsheet as of 03/31/2010 Funding_after_conversion.xls Other Public
Quarterly Progress Report for period ending 12/31/2009 qtrly_rpt_2009-12-31.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 9/30/2008 qtrly_rpt_09-30-08.pdf Quarterly Progress Report Public
Lead Agency Acceptance Letter LeadStateAcceptanceLetter.pdf Memorandum Public
Quarterly Progress Report for period ending 3/31/2009 qtrly_rpt_03-31-09.pdf Quarterly Progress Report Public
Final Report for Experiment No. 13 FHWA-KS-08-8_FinalReport.pdf Final Report Public
Quarterly Progress Report for period ending 12/31/2008 qtrly_rpt_12-31-08.pdf Quarterly Progress Report Public
Supplemental Agreement No. 1 - 6/16/2008 sup_agreement_no1.pdf Work Plan Public
Quarterly Progress Report for period ending 3/31/2008 qtrly_rpt_03-31-08.pdf Quarterly Progress Report Public
Accelerated Testing for Studying Pavement Design and Performance for Fiscal Year 2003 Final Report FY2003_final_report.pdf Report Public
Quarterly Progress Report for period ending 12/31/2007 qtrly_rpt_12-31-07.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2008 qtrly_rpt_06-30-08.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 9/30/2006 qtrly_rpt_09-30-06.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 9/30/2007 qtrly_rpt_09-30-07.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2007 qtrly_rpt_06-30-07.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 3/31/2007 qtrly_rpt_03-31-07.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 12/31/2006 qtrly_rpt_12-31-06.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 3/31/2006 qtrly_rpt_03-31-06.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 12/31/2005 qtrly_rpt_12-31-05.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 9/30/2005 qtrly_rpt_09-30-05.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2006 qtrly_rpt_06-30-06.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2005 qtrly_rpt_6-30-05.pdf Quarterly Progress Report Public
Agreement and Proposal--FY 2003 agreement_2003.pdf Work Plan Public
Quarterly Progress Report for period ending 12/31/2004 qtrly_rpt_12-31-04.pdf Quarterly Progress Report Public
Agreement and Proposal--FY 2005-2007 agreement_fy05-07.pdf Work Plan Public
Supplemental Agreement--FY 2004 agreement_supplemental_fy04.pdf Work Plan Public
Quarterly Progress Report for period ending 9/30/2004 qtrly_rpt_09-30-04.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2004 qtrly_rpt_06-30-04.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 12/31/2003 qtrly_rpt_12-31-03.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 9/30/2003 qtrly_rpt_9-30-2003.pdf Quarterly Progress Report Public
Agreement and Proposal--FY 2004 proposal.pdf Work Plan Public
Quarterly Progress Report for period ending 6/30/2003 qtrly_rpt_06-30-03.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 3/31/2003 qtrly_rpt_03-31-03.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 3/31/2005 qtrly_rpt_03-31-05.pdf Quarterly Progress Report Public
Documents Attached
Title File/Link Type Privacy Download
Midwest States Accelerated Testing 812.pdf Solicitation Public

Midwest States Accelerated Testing

General Information
Study Number: TPF-5(048)
Lead Organization: Kansas Department of Transportation
Contract Start Date: Jul 01, 2002
Solicitation Number: 812
Partners: IADOT, KS, MO, NE, NY
Contractor(s): Kansas State University
Status: Closed
Est. Completion Date: Jun 30, 2016
Contract/Other Number:
Last Updated: Dec 08, 2017
Contract End Date: Jun 30, 2016
Financial Summary
Contract Amount: $1,937,097.00
Total Commitments Received: $1,718,772.00
100% SP&R Approval:
Contact Information
Lead Study Contact(s): Rodney Montney
rodney@ksdot.org
Phone: 785-291-3844
Commitments by Organizations
Organization Year Commitments Technical Contact Name Funding Contact Name Contact Number Email Address
Iowa Department of Transportation 2003 $66,826.00 Scott Schram -- -- -- Transfer.Research@iowadot.us
Iowa Department of Transportation 2004 $71,658.00 Scott Schram -- -- -- Transfer.Research@iowadot.us
Iowa Department of Transportation 2005 $101,582.00 Scott Schram -- -- -- Transfer.Research@iowadot.us
Iowa Department of Transportation 2006 $79,929.00 Scott Schram -- -- -- Transfer.Research@iowadot.us
Iowa Department of Transportation 2007 $79,929.00 Scott Schram -- -- -- Transfer.Research@iowadot.us
Kansas Department of Transportation 2003 $66,826.00 Andrew Gisi Rodney Montney 785-291-3844 rodney@ksdot.org
Kansas Department of Transportation 2004 $71,658.00 Andrew Gisi Rodney Montney 785-291-3844 rodney@ksdot.org
Kansas Department of Transportation 2005 $101,582.00 Andrew Gisi Rodney Montney 785-291-3844 rodney@ksdot.org
Kansas Department of Transportation 2006 $79,929.00 Andrew Gisi Rodney Montney 785-291-3844 rodney@ksdot.org
Kansas Department of Transportation 2007 $79,929.00 Andrew Gisi Rodney Montney 785-291-3844 rodney@ksdot.org
Kansas Department of Transportation 2008 $72,000.00 Andrew Gisi Rodney Montney 785-291-3844 rodney@ksdot.org
Kansas Department of Transportation 2009 $100,000.00 Andrew Gisi Rodney Montney 785-291-3844 rodney@ksdot.org
Missouri Department of Transportation 2003 $66,826.00 John Donahue Karmen Stockman 573-526-5585 karmen.stockman@modot.mo.gov
Missouri Department of Transportation 2004 $71,658.00 John Donahue Karmen Stockman 573-526-5585 karmen.stockman@modot.mo.gov
Missouri Department of Transportation 2005 $101,582.00 John Donahue Karmen Stockman 573-526-5585 karmen.stockman@modot.mo.gov
Missouri Department of Transportation 2006 $79,929.00 John Donahue Karmen Stockman 573-526-5585 karmen.stockman@modot.mo.gov
Missouri Department of Transportation 2007 $79,929.00 John Donahue Karmen Stockman 573-526-5585 karmen.stockman@modot.mo.gov
Missouri Department of Transportation 2008 $72,000.00 John Donahue Karmen Stockman 573-526-5585 karmen.stockman@modot.mo.gov
Missouri Department of Transportation 2009 $50,000.00 John Donahue Karmen Stockman 573-526-5585 karmen.stockman@modot.mo.gov
Nebraska Department of Transportation 2003 $55,000.00 George Woolstrum Amy Starr 402-479-3687 amy.starr@nebraska.gov
Nebraska Department of Transportation 2004 $55,000.00 George Woolstrum Amy Starr 402-479-3687 amy.starr@nebraska.gov
Nebraska Department of Transportation 2005 $55,000.00 George Woolstrum Amy Starr 402-479-3687 amy.starr@nebraska.gov
New York State Department of Transportation 2009 $30,000.00 Bob Burnett Gary Frederick 518-457-4645 gary.frederick@dot.ny.gov
New York State Department of Transportation 2010 $30,000.00 Bob Burnett Gary Frederick 518-457-4645 gary.frederick@dot.ny.gov

Study Description

Study Description

This is an ongoing project that has an annual program determined by the TAC.

Objectives

To evaluate various pavement components such as bases, ACP and PCCP using full scale accelerated pavement testing as determined by the TAC.

Scope of Work

Each annual work program has a specific scope of work. See attached proposals for details.

Comments

We are soliciting new partners for experiment no. 17 titled "Well Bonded Superpave Overlays on HMA". This experiment will involve a Laboratory phase and an Accelerated Pavement Testing phase that will run concurrently. The Laboratory testing will evaluate bond strength using a "Pull Off" test similar to ACI 503R, Appendix A, and a special test set up for shear. The APT phase will apply 500,000 passes of an 18-kip single axle load (dual tire) to six test sections. Test sections will be constructed using two different tack materials at 3 different tack application rates. All sections will consist of a 1-1/2" Superpave overlay placed over a 2-1/2" milled surface. Cost of experiment is approximately $135,000. We are requesting commitments of approximately $27,000 each from four additional partners to fund this experiment.

Subjects: Pavement Design, Management, and Performance

Title File/Link Type Private
Final Report for Experiment No. 13 FHWA-KS-08-8_FinalReport.pdf Final Report Public
Midwest States Accelerated Testing Program Well Bonded Superpave Overlays on Hot Mix Asphalt Final REport Midwest States Accelerated Testing Program_FinalReport.pdf Final Report Public
Lead Agency Acceptance Letter LeadStateAcceptanceLetter.pdf Memorandum Public
TPF-5(048) Closeout Letter TPF-5(048) Closeout Letter - Signed.pdf Memorandum Public
Funding Spreadsheet as of 03/31/2010 Funding_after_conversion.xls Other Public
Funding After Conversion TPF-5(048)Fundingafterconversion.xls Other Public
Funding after conversion Sept 2011 TPF-5(048) Funding after conversion .pdf Other Public
Midwest States Accelerated Testing Program Well Bonded Superpave Overlays on Hot Mix Asphalt Summary Report Midwest States Accelerated Testing Prog_Final Report Summary.pdf Other Public
TPF-5(048) Closeout Funding Spreadsheet TPF-5(048) Closoeut Funding Spreadsheet.pdf Other Public
Quarterly Progress Report for period ending 9/30/2003 qtrly_rpt_9-30-2003.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 12/31/2003 qtrly_rpt_12-31-03.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2004 qtrly_rpt_06-30-04.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 9/30/2004 qtrly_rpt_09-30-04.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 3/31/2003 qtrly_rpt_03-31-03.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2003 qtrly_rpt_06-30-03.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 12/31/2004 qtrly_rpt_12-31-04.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 3/31/2005 qtrly_rpt_03-31-05.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2005 qtrly_rpt_6-30-05.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 9/30/2005 qtrly_rpt_09-30-05.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 12/31/2005 qtrly_rpt_12-31-05.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 3/31/2006 qtrly_rpt_03-31-06.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2006 qtrly_rpt_06-30-06.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 9/30/2006 qtrly_rpt_09-30-06.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 12/31/2006 qtrly_rpt_12-31-06.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 3/31/2007 qtrly_rpt_03-31-07.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2007 qtrly_rpt_06-30-07.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 9/30/2007 qtrly_rpt_09-30-07.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 12/31/2007 qtrly_rpt_12-31-07.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 3/31/2008 qtrly_rpt_03-31-08.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2008 qtrly_rpt_06-30-08.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 9/30/2008 qtrly_rpt_09-30-08.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 12/31/2008 qtrly_rpt_12-31-08.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 3/31/2009 qtrly_rpt_03-31-09.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2009 qtrly_rpt_2009-06-30.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 9/30/2009 qtrly_rpt_2009-09-30.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 12/31/2009 qtrly_rpt_2009-12-31.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 03/31/2010 quarterly_report_03-31-10.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2010 SPR_quarterly_report_TPF-5(048)_06-30-10.pdf Quarterly Progress Report Public
Quarterly Report: October 2010 - December 2010 SPRquarterlyreportTPF-5(048)12-31-10.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 3/31/2011 SPR quarterly report TPF-5(048) 3-31-11.pdf Quarterly Progress Report Public
Quarterly Progress Report for period ending 6/30/2011 SPR_quarterly_report_TPF-5(048)_06-30-11.pdf Quarterly Progress Report Public
Quarterly Report for period ending 9/30/2011 SPR_quarterly_report_TPF-5(048) 9-30-11.pdf Quarterly Progress Report Public
Quarterly Report for period ending 12/31/2011 SPR_quarterly_report_TPF-5(048) 12-31-11.pdf Quarterly Progress Report Public
Quarterly Report for period ending 3/31/2012 SPR_quarterly_report_TPF-5(048) 3-31-12.pdf Quarterly Progress Report Public
Quarterly Report June 2012 SPR_quarterly_report_TPF-5(048) 6-30-12.pdf Quarterly Progress Report Public
Sept 2012 Quarterly Report SPR_quarterly_report_TPF-5(048) 9-30-12.pdf Quarterly Progress Report Public
Quarterly Report for perod ending 3/31/13 SPR_quarterly_report_TPF-5(048) 03-31-13.pdf Quarterly Progress Report Public
Quarterly Report June 2013 SPR_quarterly_report_TPF-5(048) 06-30-13 (2).pdf Quarterly Progress Report Public
Quarterly Report September 2013 SPR_quarterly_report_TPF-5(048) 09-30-13 (2).pdf Quarterly Progress Report Public
Quarterly Report December 2013 SPR_quarterly_report_TPF-5(048) 12-31-13.pdf Quarterly Progress Report Public
Quarterly REport March 2104 SPR_quarterly_report_TPF-5(048) 03-31-14 (2).pdf Quarterly Progress Report Public
Quarterly Report June 2014 SPR_quarterly_report_TPF-5(048) 06-30-14 (2).pdf Quarterly Progress Report Public
Quarterly Report Sept 2014 SPR_quarterly_report_TPF-5(048) 09-30-14.pdf Quarterly Progress Report Public
Quarterly Report Dec 2014 SPR_quarterly_report_TPF-5(048) 12-31-14.pdf Quarterly Progress Report Public
Quarterly REport March 2015 SPR_quarterly_report_TPF-5(048)_3-31-15.pdf Quarterly Progress Report Public
Quarterly Report June 2015 SPR_quarterly_report_TPF-5(048)_6-30-15.pdf Quarterly Progress Report Public
Quarterly Report Sept 2015 SPR_quarterly_report_TPF-5(048)_9-30-15 (2).pdf Quarterly Progress Report Public
Quarterly Report Dec 2015 SPR_quarterly_report_TPF-5(048)_12-31-15.pdf Quarterly Progress Report Public
Quarterly Report SPR_quarterly_report_TPF-5(048)_03-31-16.pdf Quarterly Progress Report Public
June 2016 Quarterly Report SPR_quarterly_report_TPF-5(048)_06-30-16.docx Quarterly Progress Report Public
Quarterly REport 2016 SPR_quarterly_report_TPF-5(048)_09-30-16.pdf Quarterly Progress Report Public
Quarterly Report Jan 2017 SPR_quarterly_report_TPF-5(048)_12-31-16 (2).pdf Quarterly Progress Report Public
Accelerated Testing for Studying Pavement Design and Performance for Fiscal Year 2003 Final Report FY2003_final_report.pdf Report Public
Agreement and Proposal--FY 2003 agreement_2003.pdf Work Plan Public
Agreement and Proposal--FY 2004 proposal.pdf Work Plan Public
Supplemental Agreement--FY 2004 agreement_supplemental_fy04.pdf Work Plan Public
Agreement and Proposal--FY 2005-2007 agreement_fy05-07.pdf Work Plan Public
Supplemental Agreement No. 1 - 6/16/2008 sup_agreement_no1.pdf Work Plan Public
Title File/Link Type Private
Midwest States Accelerated Testing 812.pdf Solicitation Public